Progress photo 139

Progress Photo Collection

6th November 2019
Overview.
Sewerage treatment plant (STP) work in progress.
Carpark painting work in progress.
Podium work in progress.
5th October 2019
Overview.
Sewer pipe work in progress.
Construction sewerage treatment plant (STP) in progress.
Landscaping in progress.
6th September 2019
Overview.
Carpark floor screeding work in progress
External drainage work in progress
2nd August 2019
Overview.
Swimming pool water piping work.
Painting on podium 3rd & 4th floor.
External drainage work.
20th June 2019
Brickwork @ staircase in progress
Lift lobby tiling work
Overview of the site
9th April 2019
Commercial shop lot external wall plastering work in progress
1 Dec 2017 - Retaining wall capping beam casted
1 Nov 2017 - Retaining wall capping beam work in progress
1 Oct 2017 - Photo 1 & 2 - Retaining wall capping beam work in progress
1 July 2017 - Cassion-Pile System retaining wall reaching 85% completion.
1 June 2017 - Cassion-Pile System retaining wall reaching 80% completion.
16 May 2017 - Cassion-Pile System retaining wall reaching 71% completion.
20 April 2017 - Cassion-Pile System retaining wall reaching 63% completion.
27 March 2017 - Cassion-Pile System retaining wall still in progress
25 November 2016 - Caisson-Pile System retaining wall in progress