Progress photo 65

Progress Photo Collection

6th November 2019
Overview.
Sewerage treatment plant (STP) work in progress.
Carpark painting work in progress.
Podium work in progress.
5th October 2019
Overview.
Sewer pipe work in progress.
Construction sewerage treatment plant (STP) in progress.
Landscaping in progress.
6th September 2019
Overview.
Carpark floor screeding work in progress
External drainage work in progress
2nd August 2019
Overview.
Swimming pool water piping work.
Painting on podium 3rd & 4th floor.
External drainage work.
20th June 2019
Brickwork @ staircase in progress
Lift lobby tiling work
Overview of the site
9th April 2019
Commercial shop lot external wall plastering work in progress
09 April 2019
Corridor's plaster ceiling work at 6th floor.
12 March 2019
Electrical wiring work has been progressed up to 17th floor
Aluminium frame work has been progressed up to 16th floor
Floor tiling work has been progressed up to 16th floor
Site overview
12th February 2019
Brickwork of the commercial shop lot in progress.
Floor tiling work has been progressed up to 15th floor
Brickwork has been progressed up to 25th floor
11 December 2018
Floor tiles, Window frame & Plaster ceiling installation work in progress
Window frame installation work in progress (9th floor)
Plaster ceiling installation work in progress (10th floor)
Overview of the site
6th September 2018
Amneties floor slab (future gym + swimming pool)
1st August 2018
20th floor slab rebar & formwork in progress.
21st Floor View
Overview of site
2nd July 2018
17th floor slab rebar & formwork in progress.
Overview of site
1st June 2018
14th floor slab rebar & formwork in progress.
Overview of site
7th May 2018
12th floor slab rebar & formwork in progress.
2nd April 2018
10th floor slab casted.
Overview of site
1st March 2018
Commercial shop ground beam's rebar & formwork in progress.
Commercial shop ground slab's lean concrete casted
Overview of site
1st February 2018
7th floor slab rebar & formwork in progress.
Overview of site
5 January 2018
6th floor slab casted
1 December 2017
Commercial shop ground floor slab casted
1 November 2017
2nd Floor slab rebar & formwork in progress
1 October 2017
Ground floor slab rebar & formwork in progress.
2nd floor slab rebar & formwork in progress.
1 September 2017
Ground floor slab concrete casting work in progress
1st floor slab casted (partial).
1 August 2017
Ground beam, slab & column work in progress.
1 July 2017
Ground beam, ground slab & ground column in progress.
1 June 2017
Ground beam, ground slab & retaining wall in progress.
16 May 2017
Ground beam, ground slab & earth back-filling works in progress.
20 April 2017
Ground beam concrete casting & rebar works in progress.
27 March 2017
Overall site view
Steel bar fabrication in progress
Concrete mixing in progress
Contractor site office
25 November 2016
Column stump casted
11 May 2016
Pile Cap Casting in progress
17 April 2016
Site Preparation
18 March 2016
Site Preparation